What Is a Building Permit and Do I Need One?
A building permit is a formal authorisation issued by a Registered Building Surveyor (RBS). It confirms the proposed construction complies with the National Construction Code (NCC) and relevant Australian Standards. It also covers local government requirements. It is distinct from a planning permit, which concerns land use and design. A building permit concerns construction standards and safety.
Who Issues a Building Permit?
In Victoria, a building permit must be issued by a Registered Building Surveyor. That is either a municipal building surveyor employed by your local council or a private surveyor you appoint. Private surveyors handle the majority of residential building permit applications. They are independent statutory authorities, not agents of the builder or the council. Their role is to assess compliance and conduct mandatory inspections. They ultimately issue the occupancy permit or certificate of final inspection.
The property owner (or their authorised agent) is responsible for appointing the RBS. Your architect or building designer will typically assist in identifying and engaging an appropriate surveyor.
When Is a Building Permit Required?
A building permit is required for most construction work, including:
- Construction of a new dwelling
- Alterations and additions to an existing dwelling
- Demolition of a building or part of a building
- Construction of a garage, carport, or outbuilding over 10 square metres in floor area
- Construction of a swimming pool or spa
- Re-roofing (in some circumstances)
- Underpinning or significant structural alterations
Exemptions exist for minor work. Examples are garden sheds under 10 square metres and certain fences. So are minor repairs that do not affect structural integrity. Like-for-like replacements of non-structural elements are also exempt. If you are uncertain, check with your RBS or council before commencing work.
Mandatory Inspections for Class 1 Buildings
The building surveyor conducts or authorises mandatory inspections at specified stages of construction:
- 1Footing inspection: before concrete is poured, confirming footing dimensions and reinforcement comply with the engineer's specification
- 2Frame inspection: once framing is complete and before it is enclosed, confirming structural integrity, tie-downs, and bracing
- 3Final inspection: on completion of all works, confirming the building complies with the permit
Additional inspections may be required for specific elements, such as slab on ground, fire-rated systems, or waterproofing. It depends on the project.
How Much Does a Building Permit Cost?
Private building surveyors set their own fees, so ask two or three for a quote. The fixed parts are the state building permit levy and the council lodgement fee. The levy scales with the cost of the work. The surveyor usually collects both along with their own fee.
The Relationship Between Planning and Building Permits
A planning permit (where required) must be obtained before a building permit can be issued. The building permit application must be consistent with the approved planning permit. Your architect will manage the sequencing of these applications to avoid unnecessary delays.
Penalties for Building Without a Permit
Building without a required permit is an offence under the Building Act 1993. Council or the Building Commission Victoria can issue notices to show cause and stop work orders. They can ultimately require demolition. At sale, unapproved works may appear on a section 32 statement or in a building inspection report. That can significantly affect contract negotiations or cause a sale to collapse.
The cost of retrospective permit applications, where permitted, is typically higher than a standard application. Some councils do not accept them for structural work that cannot be inspected.
Occupancy Permit
On completion, the building surveyor issues an occupancy permit for new buildings or new habitable spaces. Alterations that create no new habitable space get a certificate of final inspection instead. The occupancy permit confirms the building is suitable for occupation. It is a required document at property sale.